Kankakee County Prevailing Wage for October 2010

Trade Name           RG TYP C Base   FRMAN *M-F>8 OSA OSH H/W   Pensn  Vac  Trng  
==================== == === = ====== ====== ===== === === ===== ===== ===== ===== 
ASBESTOS ABT-GEN        BLD   31.700 32.700 1.5   1.5 2.0 7.590 9.600 0.000 1.100 
ASBESTOS ABT-GEN        HWY   32.210 33.210 1.5   1.5 2.0 7.590 9.600 0.000 0.800 
ASBESTOS ABT-MEC        BLD   31.540  0.000 1.5   1.5 2.0 9.670 9.610 0.000 0.520 
BOILERMAKER             BLD   43.020 46.890 2.0   2.0 2.0 6.720 9.890 0.000 0.350 
BRICK MASON             BLD   38.020 40.020 1.5   1.5 2.0 6.900 9.380 0.000 0.550 
CARPENTER               BLD   35.050 37.050 1.5   1.5 2.0 8.000 12.44 0.000 0.490 
CARPENTER               HWY   34.690 36.690 1.5   1.5 2.0 8.000 12.44 0.000 0.490 
CEMENT MASON            BLD   38.020 40.020 1.5   1.5 2.0 6.900 9.380 0.000 0.550 
CERAMIC TILE FNSHER     BLD   34.220  0.000 1.5   1.5 2.0 6.900 9.380 0.000 0.550 
COMMUNICATION TECH      BLD   31.200 32.700 1.5   1.5 2.0 9.670 9.640 0.000 0.310 
ELECTRIC PWR EQMT OP    ALL   40.850 46.430 1.5   1.5 2.0 10.27 12.98 0.000 0.310 
ELECTRIC PWR GRNDMAN    ALL   31.860 46.430 1.5   1.5 2.0 8.010 10.13 0.000 0.240 
ELECTRIC PWR LINEMAN    ALL   40.850 46.430 1.5   1.5 2.0 10.27 12.98 0.000 0.310 
ELECTRICIAN             BLD   39.100 42.620 1.5   1.5 2.0 11.77 14.21 0.000 0.400 
ELEVATOR CONSTRUCTOR    BLD   37.850 42.580 2.0   2.0 2.0 10.03 9.460 2.270 0.000 
GLAZIER                 BLD   38.000 39.500 1.5   2.0 2.0 10.19 13.64 0.000 0.790 
HT/FROST INSULATOR      BLD   42.050 44.550 1.5   1.5 2.0 9.670 10.81 0.000 0.520 
IRON WORKER             ALL   37.000 40.700 2.0   2.0 2.0 8.140 18.09 0.000 0.600 
LABORER                 BLD   30.700 31.700 1.5   1.5 2.0 7.590 9.600 0.000 0.800 
LABORER                 HWY   31.210 32.210 1.5   1.5 2.0 7.590 9.600 0.000 0.800 
LABORER, SKILLED        BLD   30.700 31.700 1.5   1.5 2.0 7.590 9.600 0.000 0.800 
LABORER, SKILLED        HWY   31.210 32.210 1.5   1.5 2.0 7.590 9.600 0.000 0.800 
LATHER                  BLD   35.050 37.050 1.5   1.5 2.0 8.000 12.44 0.000 0.490 
MACHINIST               BLD   43.160 45.160 1.5   1.5 2.0 7.640 8.700 0.000 0.000 
MARBLE FINISHERS        BLD   34.220  0.000 1.5   1.5 2.0 6.900 9.380 0.000 0.550 
MARBLE MASON            BLD   38.020 40.020 1.5   1.5 2.0 6.900 9.380 0.000 0.550 
MATERIAL TESTER I       ALL   21.550  0.000 1.5   1.5 2.0 7.460 4.840 0.000 0.170 
MATERIALS TESTER II     ALL   26.550  0.000 1.5   1.5 2.0 7.460 4.840 0.000 0.170 
MILLWRIGHT              BLD   35.050 37.050 1.5   1.5 2.0 8.000 12.44 0.000 0.490 
OPERATING ENGINEER      BLD 1 45.100 49.100 2.0   2.0 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      BLD 2 43.800 49.100 2.0   2.0 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      BLD 3 41.250 49.100 2.0   2.0 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      BLD 4 39.500 49.100 2.0   2.0 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      BLD 5 48.850 49.100 2.0   2.0 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      BLD 6 46.100 49.100 2.0   2.0 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      BLD 7 48.100 49.100 2.0   2.0 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      HWY 1 43.300 47.300 1.5   1.5 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      HWY 2 42.750 47.300 1.5   1.5 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      HWY 3 40.700 47.300 1.5   1.5 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      HWY 4 39.300 47.300 1.5   1.5 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      HWY 5 38.100 47.300 1.5   1.5 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      HWY 6 46.300 47.300 1.5   1.5 2.0 11.70 8.050 1.900 1.150 
OPERATING ENGINEER      HWY 7 44.300 47.300 1.5   1.5 2.0 11.70 8.050 1.900 1.150 
PAINTER                 ALL   31.700 33.700 1.5   1.5 1.5 8.100 8.200 0.000 1.000 
PAINTER SIGNS           BLD   31.740 35.640 1.5   1.5 1.5 2.600 2.540 0.000 0.000 
PILEDRIVER              BLD   35.050 37.050 1.5   1.5 2.0 8.000 12.44 0.000 0.490 
PIPEFITTER              BLD   42.380 44.380 1.5   1.5 2.0 11.03 11.00 0.000 1.310 
PLASTERER               BLD   38.020 40.020 1.5   1.5 2.0 6.900 9.380 0.000 0.550 
PLUMBER                 BLD   41.610 43.610 1.5   1.5 2.0 9.500 10.00 0.000 1.310 
ROOFER                  BLD   37.650 40.650 1.5   1.5 2.0 7.750 6.570 0.000 0.430 
SHEETMETAL WORKER       BLD   41.660 43.660 1.5   1.5 2.0 8.810 10.66 0.000 0.780 
SIGN HANGER             BLD   35.050 37.050 1.5   1.5 2.0 8.000 12.44 0.000 0.490 
SPRINKLER FITTER        BLD   36.140 38.890 1.5   1.5 2.0 8.200 6.550 0.000 0.250 
TERRAZZO FINISHER       BLD   34.220  0.000 1.5   1.5 2.0 6.900 9.380 0.000 0.550 
TERRAZZO MASON          BLD   38.020 40.020 1.5   1.5 2.0 6.900 9.380 0.000 0.550 
TILE MASON              BLD   38.020 40.020 1.5   1.5 2.0 6.900 9.380 0.000 0.550 
TRUCK DRIVER            ALL 1 28.870 29.420 1.5   1.5 2.0 6.690 4.150 0.000 0.000 
TRUCK DRIVER            ALL 2 29.070 29.420 1.5   1.5 2.0 6.690 4.150 0.000 0.000 
TRUCK DRIVER            ALL 3 29.270 29.420 1.5   1.5 2.0 6.690 4.150 0.000 0.000 
TRUCK DRIVER            ALL 4 29.420 29.420 1.5   1.5 2.0 6.690 4.150 0.000 0.000 
TUCKPOINTER             BLD   38.020 40.020 1.5   1.5 2.0 6.900 9.380 0.000 0.550 

Legend:  M-F>8 (Overtime is required for any hour greater than 8 worked
each day, Monday through Friday.
OSA  (Overtime is required for every hour worked on Saturday)
OSH  (Overtime is required for every hour worked on Sunday and Holidays)
H/W  (Health & Welfare Insurance)
Pensn (Pension)
Vac (Vacation)
Trng (Training)

        

Explanations

KANKAKEE COUNTY

The following list is considered as those days for which holiday rates
of wages for work performed apply: New Years Day, Memorial/Decoration
Day, Fourth of July, Labor Day, Veterans Day, Thanksgiving Day,
Christmas Day. Generally, any of these holidays which fall  on a
Sunday is celebrated on the following Monday.  This then makes work
performed on that Monday payable at the appropriate overtime rate for
holiday pay.   Common practice in a given local may alter certain days
of celebration such as the day after Thanksgiving for Veterans Day.
If in doubt, please check with IDOL.


EXPLANATION OF CLASSES

ASBESTOS - GENERAL - removal of asbestos material/mold and hazardous
materials from any place in a building, including mechanical systems
where those mechanical systems are to be removed.  This includes the
removal of asbestos materials/mold and hazardous materials from
ductwork or pipes in a building when the building is to be demolished
at the time or at some close future date.

ASBESTOS - MECHANICAL - removal of asbestos material from mechanical
systems, such as pipes, ducts, and boilers, where the mechanical
systems are to  remain.

CERAMIC TILE FINISHER, MARBLE FINISHER, AND TERRAZZO FINISHER

The laying, setting and finishing of all tile where used for floors,
walls, ceilings, walks, promenade roofs, stair treads, stair risers,
facings, hearths, fireplaces, and decorative inserts, together with
any marble plinths, thresholds or window stools used in connection
with any tile work; also to prepare and set all concrete, cement,
brickwork, or other foundation or materials that may be required to
properly set and complete such work; the setting or bedding of all
tiling, stone, marble, composition, glass, mosaic, or other materials
forming the facing, hearth or fireplace of a mantle, or the mantle
complete, together with the setting of all cement, brickwork, or other
material required in connection with the above work; also the
slabbing and fabrication of tile mantels, counters and tile panels of
every description and the erection and installation of same and the
building, shaping, forming, construction, or repairing of all
fireplace work, whether in connection with the mantle hearth facing or
not, and the setting and preparing of all material, such as cement,
plaster, mortar, brickwork, iron work or other materials necessary for
the proper and safe construction and completion of such work.  The
term "Ceramic" is used for naming the classification only and is in no
way a limitation of the product handled.  Ceramic takes into
consideration most hard tiles.

COMMUNICATIONS TECHNICIAN

Installing, manufacturing, assembling and maintaining sound and
intercom, protection alarm (security), fire alarm, master antenna
television, closed  circuit television, low voltage control for
computers and/or door monitoring, school communications systems,
telephones and servicing of nurse and emergency  calls, and the
installation and maintenance of transmit and receive antennas,
transmitters, receivers, and associated apparatus which operates in
conjunction  with above systems.  All work associated with these
system installations will be included EXCEPT the installation of
protective metallic conduit in new  construction projects (excluding
less than ten-foot, runs strictly for protection of cable) and 120
volt AC (or higher) power wiring and associated hardware.

LABORER, SKILLED - BUILDING

The skilled laborer building (BLD) classification shall encompass the
following types of work, irrespective of the site of the work: caisson
workers plus depth, gunnite nozzle men, lead man on sewer work,
welders, cutters, burners and torchmen, chain saw operators, paving
breaker, jackhammer and drill operators, layout man and/or drainage
tile layer, steel form setters - street and highway, air tamping
hammerman, signal man on crane, concrete saw operator, screenman on
asphalt pavers, front end man on chip spreader, laborers tending
masons with hot materials or where foreign materials are used,
multiple concrete duct-leadman, luteman, asphalt raker, curb asphalt
machine operator, ready mix scalemen (permanent, portable or temporary
plant), laborers handling masterplate or similar materials, laser
beam operator, concrete burning machine operator, coring machine
operator, plaster tenders, underpinning and shoring of buildings,
material selector when working with fire-brick or castable material,
fire watch, signaling of all power equipment, and tree topper or
trimmer when in connection with construction.

LABORER, SKILLED - HIGHWAY

The skilled laborer heavy and highway (HWY) classification shall
encompass the following types of work, irrespective of the site of the
work: handling of materials treated with oil, creosote, asphalt
and/or any foreign materials harmful to skin or clothing, track
laborers, chloride handlers, the unloading and loading with steel
workers and re-bars, concrete workers (wet), tunnel helpers in free
air, batch dumpers, mason tenders, kettle and tar men, plastic
installers, scaffold workers, motorized buggies or motorized unit used
for wet concrete or handling of building materials, laborers with
de-watering systems, sewer workers plus depth, rod and chainmen,
vibrator operators, mortar mixer operators, cement silica, clay, fly
ash, lime and plasters, handlers (bulk or bag), cofferdam workers plus
depth, on concrete paving, placing, cutting and tying or reinforcing,
deck hand, dredge hand shore laborers, bankmen on floating plant,
asphalt workers with machine, and layers, grade checker, power tools,
stripping of all concrete forms excluding paving forms, dumpmen and
spotters, when necessary, caisson workers plus depth, gunnite nozzle
men, welders, cutters, burners and torchmen, chain saw operators,
paving breaker, jackhammer and drill operators, layout man and/or
drainage tile layer, steel form setters - street and highway, air
tamping hammerman, signal man on crane, concrete saw operator,
screedman on asphalt pavers, front end man on chip spreader, multiple
concrete duct, luteman, asphalt raker, curb asphalt machine operator,
ready mix scalemen (portable or temporary plant), laser beam operator,
concrete burning machine operator, and coring machine operator.

MATERIAL TESTER I:  Hand coring and drilling for testing of materials;
field inspection of uncured concrete and asphalt.

MATERIAL TESTER II:  Field inspection of welds, structural steel,
fireproofing, masonry, soil, facade, reinforcing steel, formwork,
cured concrete, and concrete and asphalt batch plants; adjusting
proportions of bituminous mixtures.


OPERATING ENGINEER - BUILDING

Class 1. Asphalt Plant; Asphalt Spreader; Autograde; Backhoes with
Caisson Attachment; Batch Plant; Benoto (requires Two Engineers);
Boiler and Throttle Valve; Caisson Rigs; Central Redi-Mix Plant;
Combination Back Hoe Front End-loader Machine; Compressor and Throttle
Valve; Concrete Breaker (Truck Mounted); Concrete Conveyor; Concrete
Conveyor (Truck Mounted); Concrete Paver Over 27E cu. ft; Concrete
Paver 27E cu. ft. and Under: Concrete Placer; Concrete Placing Boom;
Concrete Pump (Truck Mounted); Concrete Tower; Cranes, All; Cranes,
Hammerhead; Cranes. (GCI and similar Type); Creter Crane; Crusher,
Stone, etc.; Derricks, All; Derricks, Traveling; Formless Curb and
Gutter Machine; Grader, Elevating; Grouting Machines; Highlift Shovels
or Front Endloader 2-1/4 yd. and over; Hoists, Elevators, outside
type rack and pinion and similar machines; Hoists, One, Two and Three
Drum; Hoists, Two Tugger One Floor; Hydraulic Backhoes; Hydraulic Boom
Trucks; Locomotives, All; Motor Patrol; Lubrication Technician;
Manipulators; Pile Drivers and Skid Rig; Post Hole Digger; Pre-Stress
Machine; Pump Cretes Dual Ram; Pump Cretes: Squeeze Cretes-Screw Type
Pumps; Gypsum Bulker and Pump; Raised and Blind Hole Drill; Roto Mill
Grinder; Scoops - Tractor Drawn; Slip-Form Paver; Straddle Buggies;
Tournapull; Tractor with Boom and Side Boom; Trenching Machines.

Class 2. Boilers; Broom, All Power Propelled; Bulldozers; Concrete
Mixer (Two Bag and Over); Conveyor, Portable; Forklift Trucks;
Highlift Shovels or Front Endloaders under 2-1/4 yd.; Hoists,
Automatic; Hoists, Inside Elevators; Hoists, Sewer Dragging Machine;
Hoists, Tugger Single Drum; Rock Drill (Truck Mounted); Rollers, All;
Steam Generators; Tractors, All; Tractor Drawn Vibratory Roller; Winch
Trucks with "A" Frame.

Class 3. Air Compressor; Combination Small Equipment Operator;
Generators; Heaters, Mechanical; Hoists, Inside Elevators; Hydraulic
Power Units (Pile Driving, Extracting, and Drilling); Pumps, over 3"
(1 to 3 not to exceed a total of 300 ft.); Low Boys; Pumps, Well
Points; Welding Machines (2 through 5); Winches, 4 Small Electric
Drill Winches; Bobcats (up to and including ¾ cu yd.).

Class 4.
Oilers and Brick Forklift.

Class 5. Assistant Craft Foreman.

Class 6. Gradall	

Class 7. Mechanics


OPERATING ENGINEERS - HIGHWAY CONSTRUCTION

Class 1. Asphalt Plant; Asphalt Heater and Planer Combination; Asphalt
Heater Scarfire; Asphalt Spreader; Autograder/GOMACO or other similar
type machines: ABG Paver; Backhoes with Caisson Attachment; Ballast
Regulator: Belt Loader; Caisson Rigs; Car Dumper; Central Redi-Mix
Plant; Combination Backhoe Front Endloader Machine, (1 cu. yd. Backhoe
Bucket or over or with attachments); Concrete Breaker (Truck
Mounted); Concrete Conveyor; Concrete Paver over 27E cu. ft.; Concrete
Placer; Concrete Tube Float; Cranes, all attachments; Cranes, Tower
Cranes of all types: Creter Crane: Crusher, Stone, etc.; Derricks,
All; Derrick Boats; Derricks, Traveling; Dredges; Formless Curb and
Gutter Machine; Grader, Elevating; Grader, Motor Grader, Motor Patrol,
Auto Patrol, Form Grader, Pull Grader, Subgrader; Guard Rail Post
Driver Truck Mounted; Hoists, One, Two and Three Drum; Hydraulic
Backhoes; Backhoes with shear attachments; Lubrication Technician;
Manipulators; Mucking Machine; Pile Drivers and Skid Rig; Pre-Stress
Machine; Pump Cretes Dual Ram; Rock Drill - Crawler or Skid Rig; Rock
Drill- Truck Mounted; Rock/Track Tamper; Roto Mill Grinder; Slip-Form
Paver; Soil Test Drill Rig (Truck Mounted); Straddle Buggies;
Hydraulic Telescoping Form (Tunnel); Tractor Drawn Belt Loader (with
attached pusher - two engineers); Tractor with Boom; Tractaire with
Attachments; Trenching Machine; Truck Mounted Concrete Pump with Boom;
Raised or Blind Hole Drills (Tunnel Shaft); Underground Boring and/or
Mining Machines 5 ft. in diameter and over tunnel, etc; Underground
Boring and/or Mining Machines under 5 ft. in diameter; Wheel
Excavator; Widener (APSCO).

Class 2. Batch Plant; Bituminous Mixer; Boiler and Throttle Valve;
Bulldozers; Car Loader Trailing Conveyors; Combination Backhoe Front
Endloader Machine (Less than 1 cu. yd. Backhoe Bucket or over or with
attachments); Compressor and Throttle Valve; Compressor, Common
Receiver (3); Concrete Breaker or Hydro Hammer; Concrete Grinding
Machine; Concrete Mixer or Paver 7S Series to and including 27 cu.
ft.; Concrete Spreader; Concrete Curing Machine, Burlap Machine,
Belting Machine and Sealing Machine; Conveyor Muck Cars (Haglund or
Similar Type); Drills, All; Finishing Machine - Concrete; Highlift
Shovels or Front Endloader; Hoist - Sewer Dragging Machine; Hydraulic
Boom Trucks (All Attachments); Hydro-Blaster; All Locomotives, Dinky;
Off-Road Hauling Units (including articulating) / 2 ton capacity or
more; Non Self-Loading Ejection Dump; Pump Cretes: Squeeze Cretes -
Screw Type Pumps, Gypsum Bulker and Pump; Roller, Asphalt; Rotary Snow
Plows; Rototiller, Seaman, etc., self-propelled; Scoops - Tractor
Drawn; Self-Propelled Compactor; Spreader - Chip - Stone, etc.;
Scraper; Scraper - Prime Mover in Tandem (Regardless of Size): Tank
Car Heater; Tractors, Push, Pulling Sheeps Foot, Disc, Compactor,
etc.; Tug Boats.

Class 3. Boilers; Brooms, All Power Propelled; Cement Supply Tender;
Compressor, Common Receiver (2); Concrete Mixer (Two Bag and Over);
Conveyor, Portable; Farm-Type Tractors Used for Mowing, Seeding, etc.;
Fireman on Boilers; Forklift Trucks; Grouting Machine; Hoists,
Automatic; Hoists, All Elevators; Hoists, Tugger Single Drum; Jeep
Diggers; Low Boys; Pipe Jacking Machines; Post-Hole Digger; Power Saw,
Concrete Power Driven; Pug Mills; Rollers, other than Asphalt; Seed
and Straw Blower; Steam Generators; Stump Machine; Winch Trucks with
"A" Frame; Work Boats; Tamper-Form-Motor Driven.

Class 4. Air Compressor; Combination - Small Equipment Operator;
Directional Boring Machine; Generators; Heaters, Mechanical; Hydraulic
Power Unit (Pile Driving, Extracting, or Drilling); Hydro- Blaster;
Light Plants, All (1 through 5); Pumps, over 3" (1 to 3 not to exceed
a total of 300 ft.); Pumps, Well Points; Tractaire; Welding Machines
(2 through 5); Winches, 4 Small Electric Drill Winches.

Class 5. Oilers and Directional Boring Machine Locator.

Class 6. Field Mechanics and Field Welders.

Class 7. Gradall and machines of like nature.


TRUCK DRIVER - BUILDING, HEAVY AND HIGHWAY CONSTRUCTION
Class 1.  Two or three Axle Trucks.  A-frame Truck when used for
transportation purposes; Air Compressors and Welding Machines,
including those pulled by  cars, pick-up trucks and tractors;
Ambulances; Batch Gate Lockers; Batch Hopperman; Car and Truck
Washers; Carry-alls; Fork Lifts and Hoisters; Helpers;  Mechanics
Helpers and Greasers; Oil Distributors 2-man operation; Pavement
Breakers; Pole Trailer, up to 40 feet; Power Mower Tractors;
Self-propelled Chip  Spreader; Skipman; Slurry Trucks, 2-man
operation; Slurry Truck Conveyor Operation, 2 or 3 man; Teamsters;
Unskilled dumpman; and Truck Drivers hauling  warning lights,
barricades, and portable toilets on the job site.

Class 2.  Four axle trucks; Dump Crets and Adgetors under 7 yards;
Dumpsters, Track Trucks, Euclids, Hug Bottom Dump Turnapulls or
Turnatrailers when pulling  other than self-loading equipment or
similar equipment under 16 cubic yards; Mixer Trucks under 7 yeards;
Ready-mix Plant Hopper Operator, and Winch Trucks,  2 Axles.

Class 3.  Five axle trucks; Dump Crets and Adgetors 7 yards and over;
Dumpsters, Track Trucks, Euclids, Hug Bottom Dump Turnatrailers or
turnapulls when  pulling other than self-loading equipment or similar
equipment over 16 cubic yards; Explosives and/or Fission Material
Trucks; Mixer Trucks 7 yards or over;  Mobile Cranes while in transit;
Oil Distributors, 1-man operation; Pole Trailer, over 40 feet; Pole
and Expandable Trailers hauling material over 50 feet long; Slurry
trucks, 1-man operation; Winch trucks, 3 axles or more;
Mechanic--Truck Welder and Truck Painter.

Class 4.  Six axle trucks; Dual-purpose vehicles, such as mounted
crane trucks with hoist and accessories; Foreman; Master Mechanic;
Self-loading equipment  like P.B. and trucks with scoops on the front.


Other Classifications of Work:

For definitions of classifications not otherwise set out, the
Department generally has on file such definitions which are available.
If a task to be performed is not subject to one of the
classifications of pay set out, the Department will  upon being
contacted state which neighboring county has such a classification and
provide such rate, such rate being deemed to exist by reference in
this  document.  If no neighboring county rate applies to the task,
the Department shall undertake a special determination, such special
determination  being then deemed to have existed under this
determination.  If a project requires these, or any classification not
listed, please contact IDOL at 217-782-1710 for  wage rates or
clarifications.

LANDSCAPING

Landscaping work falls under the existing classifications for laborer,
operating engineer and truck driver.  The work performed by landscape
plantsman and  landscape laborer is covered by the existing
classification of laborer.  The work performed by landscape operators
(regardless of equipment used or its size) is  covered by the
classifications of operating engineer.  The work performed by
landscape truck drivers (regardless of size of truck driven) is
covered by the  classifications of truck driver.